City permit guide · FL

EV charger permits in Orlando, FL

Orlando has one of the clearest EVCS pages in Florida: it says an EV charging station needs an electrical permit with an associated engineering permit issued to a licensed general or electrical contractor, and it lays out the ProjectDox workflow.

Quick answer for Orlando, FL

  • A new Level 2 home EV charger circuit generally requires an electrical permit in Orlando, FL.
  • Permit path: Electrical permit with associated engineering permit issued to a licensed general or electrical contractor.
  • Typical fee guidance: Per Orlando permit lookup/payment workflow after review approval..
  • Timeline: Plan-review turnaround varies by residential vs commercial scope; payment and download happen after approval.

Official source: City of Orlando EV charging station permit page

Permit required Yes — new 240V circuit
Permit type Electrical permit with associated engineering permit issued to a licensed general or electrical contractor
Typical fee Per Orlando permit lookup/payment workflow after review approval.
Apply online Yes · Portal

The process

How it works in Orlando, FL

Permit office: Orlando Permitting Services Division.

Who can pull the permit: A licensed general or electrical contractor must be associated with the permit path described by the City of Orlando..

Plan review: Signed and sealed plans/documents are required according to the city page. Project value above $5,000 triggers a recorded Notice of Commencement before work starts.

Typical timeline: Plan-review turnaround varies by residential vs commercial scope; payment and download happen after approval.

Bring these

Documents you'll need

  • Charger manufacturer spec sheet showing listing, amperage, connector, and hardwired vs plug-in configuration
  • Panel photo and breaker directory, plus proposed breaker size and charging load
  • Simple site sketch showing the electrical panel, wire route, charger location, and parking space served
  • Load calculation when the service is small, the circuit is 40A or larger, or a panel upgrade may be needed
  • Signed and sealed plans/documents as required
  • Recorded Notice of Commencement if project value exceeds $5,000

Final step

Inspection notes

Download approved plans, post them at the job site, schedule required inspections, and close the permit after final inspection. Orlando warns open permits can create problems during sale or refinancing.

Verified against City of Orlando EV charging station permit page on July 4, 2026. Use the linked official source because fees, portal labels, and inspection procedures can change.

Electrical work can be dangerous and is regulated by code. This page is educational, not electrical or engineering advice. Hire a licensed electrician and follow your local permitting process.

Find licensed electricians in Orlando, FL

Ask each bidder to include the permit and inspection in the quoted price — then compare like for like.

Finding an installer yourself: ask for the contractor's state license number, proof of insurance, and at least two recent Level 2 installs. Get the permit number in writing.

Use the free permit checklist

FAQ

Orlando, FL permit FAQ

Do I need a permit for a Level 2 EV charger in Orlando?

Yes. A new 240V Level 2 charger circuit is electrical work and should be permitted through Orlando Permitting Services Division. The local path is: Electrical permit with associated engineering permit issued to a licensed general or electrical contractor.

Who should pull the EV charger permit in Orlando?

A licensed general or electrical contractor must be associated with the permit path described by the City of Orlando.

How long does the Orlando EV charger permit take?

Plan-review turnaround varies by residential vs commercial scope; payment and download happen after approval.